US 64 Status Report
US 64 Nash County – Interchange at I-95 and Sunset Ave. (U-5026)
- Deliverable
- Total cost: $46.499 million (National Highway Program) Division Tier
- Unfunded: $0
- Right of Way – Beginning 2019 ($12 million)
- Construction – Beginning 2019 ($33.399 million)
Project Manager Roadway:
US 64 Nash County – Widen Bridge at Old Carriage Rd. (U-5995)
- Not Deliverable
- Total cost: $14.2 million (NC Highway Trust Fund) Division Tier
- Unfunded: $0
- Right of Way / Utilities – 2023 ($3.3 million)
- Construction – 2025 ($10.92 million)
Project Manager Roadway:
US 64 Alternate – Replace Bridge No. 29 over the Tar River (B-5670)
- Not Deliverable
- Total cost: $5.165 million (Highway Fund Bridge Program)
- Unfunded: $0
- Environmental Document – October 2021
- R/W Acquisition – 2023 ($465,000)
- Construction – 2024 ($4.65 million)
Project Manager Roadway: John Conforti, REM (919) 707-6015 jgconforti@ncdot.gov
US 64 Tyrrell County – Rehab Bridge over Alligator River (B-5936)
- Not Deliverable
- Total cost: $10.725 million (Undetermined) Statewide Tier
- Unfunded: $0
- Construction – 2025 ($10.725 million)
Project Manager Roadway:
US 64 Columbia to East of Alligator River (R-2545 AA, AB, B)
- Not Deliverable
- Total cost: $615.791 million (NC Highway Trust Fund)
- Unfunded: $611.59 million
- Currently not programmed in the 2018 – 2027 STIP
Utilities:
- Segment AA – Unfunded ($1.395 million)
- Segment AB – Unfunded ($1.611 million)
- Segment B – Unfunded ($1.156 million)
R/W Acquisition:
- Segment AA – Unfunded ($1.825 million)
- Segment AB – Unfunded ($2.025 million)
- Segment B – Unfunded ($3.175 million)
Construction:
- Segment AA – Unfunded ($24.8 million)
- Segment AB – Unfunded ($72.5 million)
- Segment B – Unfunded ($503.1 million)
Project Manager: Brian Yamamoto, P.E. (919) 707-6051 byamamoto@ncdot.gov
US 64 East Lake to Manns Harbor (R-2544 A, B, C)
- Not Deliverable
- Total cost: $98.934 million (NC Highway Trust Fund)
- Unfunded: $90.6 million
- Currently not programmed in the 2016 – 2025 STIP
Utilities:
- Segment A – Unfunded ($315,000)
- Segment B – Unfunded ($1.401 million)
- Segment C – Unfunded ($1.86 million)
R/W Acquisition:
- Segment A – Unfunded ($1.175 million)
- Segment B – Unfunded ($1.35 million)
- Segment C – Unfunded ($300,000)
Construction:
- Segment A – Unfunded ($14.7 million)
- Segment B – Unfunded ($23.3 million)
- Segment C – Unfunded ($46.2 million)
Project Manager: Brian Yamamoto, P.E. (919) 707-6051 byamamoto@ncdot.gov
US 64 Dare County – Rehab Bridge over Croatan Sound (B-5943)
- Deliverable
- Total cost: $2.45 million (NC Highway Trust Fund) Statewide Tier
- Unfunded: $0
- Construction – 2017 ($2.4 million)
Project Manager Roadway: